Koolunga:

Lower Wonga:

Calala:

MREH:

  • DA received 10 August 2023

  • DA received 14 July 2023

  • SEARS issued 30 January 2023

  • EIS submitted 10 November 2023

  • Planning overlay granted and gazetted 29 July 2021

  • EPBC approval 21 June 2023

  • 5.3.4A letters received 29 June 2023

  • Cultural Heritage Management Plan approval: 20 July 2023

Project milestones

Koolunga:

Lower Wonga:

Calala:

MREH:

  • DA received 10 August 2023

  • DA received 14 July 2023

  • SEARS issued 30 January 2023

  • EIS submitted 10 November 2023

  • Planning overlay granted and gazetted 29 July 2021

  • EPBC approval 21 June 2023

  • 5.3.4A letters received 29 June 2023

  • Cultural Heritage Management Plan approval: 20 July 2023

Project milestones

Get in touch

Energy Infrastructure Australia

Releases

News

Contact us

Ground Floor
36 Esplanade Brighton
Melbourne VIC 3186

Energy Infrastructure Australia

In the spirit of reconciliation EIA acknowledges the Traditional Custodians of Country throughout Australia and their connections to land, sea and community. We pay our respect to their Elders past and present and extend that respect to all Aboriginal and Torres Strait Islander peoples today.